Bedford Water board to consider letting Turkey Mountain tower proposal enter county permitting

Bedford Water directors are scheduled to consider an owner-authority letter that would let a proposed Turkey Mountain cellular-tower project enter Bedford County’s special-use-permit process.

Reporting standardThis article distinguishes documented facts, analysis, disputed claims, and unresolved questions. Primary records are linked where practical.
Original Unmarked Desk editorial illustration of a proposed special-use-permit step for a Turkey Mountain cellular-tower project on Bedford Water land.
Original Unmarked Desk editorial illustration. It represents a proposed public permitting step, not a site photograph or evidence of an approved or built tower.

Bedford Water’s board is scheduled to consider whether to let a proposed cellular-tower project on utility-owned land at Turkey Mountain enter Bedford County’s special-use-permit process.

The item, Resolution 2026-11.01, is listed on the agenda for the authority’s 7 p.m. Nov. 17 regular meeting. The agenda does not show that the board has approved the proposal; it lists the resolution for consideration.

According to the supporting board packet, Bedford Water has told The Towers, LLC that it will not combine lots at the Turkey Mountain Water Treatment Plant and that zoning approvals would need to come through Bedford County. The packet says an owner-authority letter from Bedford Water is needed for the county to process a special-use-permit application and hold a public hearing.

The proposed resolution would authorize the executive director to complete and submit that letter to the county. The form included in the packet is uncompleted: its motion, second and board-vote fields are blank. That means the packet documents a proposed procedural step, not a completed approval.

A Nov. 9 letter in the packet from Vertical Bridge Development asks Bedford Water to submit the owner-authority letter for a project it identifies as the Vertical Bridge/The Towers, LLC tower project. The company’s request and the authority’s proposed resolution do not establish a final tower height, site plan, lease payment, coverage benefit or construction timeline.

If directors approve the resolution, the next documented step would be a county permitting process and public hearing, not construction. The packet describes county special-use approval as a prerequisite before approval to construct the proposed tower could be granted.

The meeting is set for 7 p.m. Nov. 17 at Bedford Water’s Annex building, 1723 Falling Creek Road in Bedford County. The board’s vote, any signed owner-authority letter and any county hearing notice were not available in the records reviewed for this article.

Sources

  1. Bedford Water Nov. 17, 2026 agenda
  2. Bedford Water Nov. 17, 2026 board packet